What you need to know
As a developer, you're responsible for providing telecommunications infrastructure to your properties. Based on your individual development scenario, you may need to apply with nbn to do so. This means you’ll need to complete an nbn™ New Developments application form.
To further understand what's involved, please see our following guides.
Start preparing early
In order to meet requirements during the construction phase and obtain the approvals needed, it’s important to start planning as early as possible.
If you are building a small development, such as a sub-dividing a lot into two residential units, please allow a minimum of three months’ notice before the premises will be occupied to help ensure the network can be connected in time for new residents. For all other developments, allow a minimum of six months’ notice before service connections are required.
Please note: nbn will endeavour to achieve these timeframes, but cannot guarantee these timeframes in all cases.